Rate of A = \[ \frac{1}{20} \]
Rate of B = \[ \frac{1}{15} \]
Work done by A and B together in \(6\) days:
\[ 6\left(\frac{1}{20} + \frac{1}{15}\right) \]
LCM of \(20\) and \(15\) is \(60\):
\[ 6\left(\frac{3 + 4}{60}\right) = 6\left(\frac{7}{60}\right) = \frac{42}{60} = \frac{7}{10} \]
Remaining work:
\[ 1 - \frac{7}{10} = \frac{3}{10} \]
Now A and C finish \(\frac{3}{10}\) work in \(4\) days.
So their one-day work:
\[ \frac{3}{10} \div 4 = \frac{3}{40} \]
Thus,
\[ \frac{1}{20} + C = \frac{3}{40} \]
\[ \frac{1}{20} = \frac{2}{40} \]
\[ C = \frac{3}{40} - \frac{2}{40} = \frac{1}{40} \]
Therefore, C alone can do the work in:
\[ 40 \text{ days} \]
Correct Answer: C
A-এর কাজের হার = \[ \frac{1}{20} \]
B-এর কাজের হার = \[ \frac{1}{15} \]
A ও B একসঙ্গে \(6\) দিনে কাজ করে:
\[ 6\left(\frac{1}{20} + \frac{1}{15}\right) \]
LCM \(20\) ও \(15\) = \(60\)
\[ 6\left(\frac{3 + 4}{60}\right) = 6\left(\frac{7}{60}\right) = \frac{7}{10} \]
অবশিষ্ট কাজ:
\[ 1 - \frac{7}{10} = \frac{3}{10} \]
এখন A ও C \(4\) দিনে \(\frac{3}{10}\) কাজ শেষ করে।
এক দিনে কাজের পরিমাণ:
\[ \frac{3}{40} \]
অতএব,
\[ \frac{1}{20} + C = \frac{3}{40} \]
\[ C = \frac{1}{40} \]
সুতরাং C একা কাজটি \(40\) দিনে করতে পারবে।
সঠিক উত্তর: C
© All right Reversed.Xcelerate